St Albans council is only now hiring designers for its Verulamium Park lakes and Bell Meadow scheme. Detailed design runs to summer 2027, with consents after that.
Work to restore the silted lakes in Verulamium Park will not start for some time yet. St Albans City and District Council is still looking for a design team, almost two years after councillors approved the scheme. Detailed design is now expected to run from this winter to summer 2027, with planning consents and other approvals in 2027.
The timetable is in an update report to the council’s Public Realm Committee on 5 November.
What was approved
The committee approved the plan in January 2025. The council’s announcement at the time said it would:
- dredge the two heavily silted lakes
- use the silt to build planting beds around their edges, which would narrow the lakes
- create nature walks through the new planted areas
- turn Bell Meadow, by the St Michael’s Street entrance, into a wetland with a permanent raised footpath
The council had set aside £2.2 million and said the work would likely cost “a seven-figure sum”. It rejected the Environment Agency’s preferred option of returning the River Ver to its natural course through Bell Meadow, which would have cost £4m to £6m. The lakes were built more than 80 years ago. In January 2025 Bell Meadow was closed for safety because its path kept flooding.
Why it has taken this long
The council had planned to hire specialist designers through an Environment Agency framework contract. The report says the agency has now told the council the project “does not meet the criteria” to use it. So the council is running its own competitive procurement for a team of consultants instead.
The report gives this timetable, and says it may change:
| Stage | Expected |
|---|---|
| Finding a consultant team | Autumn and winter 2026 |
| Appointing the team | Winter 2026 |
| Detailed design | Winter 2026 to summer 2027 |
| Surveys and technical studies | Throughout the design stage |
| Consents and approvals | 2027 |
The designers will produce drawings, updated cost estimates, environmental assessments, plans for phasing the building work and advice on hiring a contractor. The report says that contractor will be chosen through an open tender. It gives no start date for the dredging and no updated cost.
What is happening on the river now
Some work along the River Ver is going ahead separately. The Countryside Management Service has got a flood risk permit from the Environment Agency for a trial in the river channel at Bell Meadow. It will install a “woody debris berm”, a bank of timber designed to encourage natural processes and improve habitat. The trial will monitor its effect on the flow and on sediment.
The report says plans are also being drawn up to formalise wetland areas and add boardwalks “where appropriate”.
What it means for you
- The lakes stay as they are for now. No dredging or building work is scheduled before the design stage finishes in 2027.
- The river trial is separate. The woody debris work at Bell Meadow has its permit, but the report gives no date for it.
- The cost is not settled. The council’s 2025 announcement said the design and tender stage would test whether the scheme “is indeed affordable”.